PROJECT:
Reconstruction of Weg naar Westpunt at Tera Kora
CLIENT:
The Ministry of Traffic, Transportation, and Spatial Planning
STARTED:
March 23, 2015
FINISHED:
October 21, 2015
DURATION:
7 months
PROJECT DESCRIPTION:
The road through Tera Kora is rebuilt. A new road is built, featuring a median strip. A clinker-brick sidewalk is built on both sides, together with 3 bus stops. In addition, junctions with adjacent roads are rebuilt and the road is provided with plastic speed bumps. Lamp posts and signage have also been placed. After new greenery has been planted and road markings have been painted, the road through Tera Kora is as good as new again.